Data Center Announcements: 6 of 25 Gave an Opening Target
By Virgo PR Editorial Team. Reviewed by Kyle Porter, Executive Vice President & Managing Director.
Updated November 21, 2026

Virgo PR reviewed 25 U.S. data center announcements from 2025. Eighteen gave a dollar figure and 13 a power figure, but only six gave an opening target, and one of those named a dependency.
Virgo PR reviewed 25 U.S. data center project announcements from 2025. Eighteen disclosed a dollar figure, 13 gave a project-specific power figure, and six gave a target for opening or starting operations. Only one of those six named a condition that could affect the timetable.
These counts describe a purposive sample of 25 projects, not the whole industry. Virgo PR checked each announcement against company filings, utility disclosures, local approvals and other records visible through November 21, 2026.
Last updated: November 21, 2026.
On this page
- What the announcements disclosed
- What a dollar figure covers
- What a megawatt number needs to say
- Construction jobs and permanent jobs
- Opening targets
- What supporting records added
- What an announcement should state
- How Virgo PR ran the review
- Frequently asked questions
What did the 25 data center announcements disclose?
Table 1 sets out each count with its denominator and the rule used to code it. The unit is the project, and each project was scored on one selected announcement.
Table 1. What the 25 announcements disclosed. Source: Virgo PR review of 25 U.S. data center announcements, records observed November 21, 2026.What the announcement disclosedCountShareWhat qualified Numeric dollar amount18 of 2572%A numerical dollar figure for investment, land, site work or the wider program. It could be a forecast, a minimum, a first-phase estimate or a completed purchase. Amount covers multiple phases6 of 1833%The figure covered more than one development tranche, including a minimum for early phases and full build-out projections. Numeric MW or GW13 of 2552%A MW or GW figure specific to the project, including utility load, critical IT load, generation and capacity without a stated basis. Separate stages of capacity5 of 1338%The release gave an early power or IT figure and a separate larger project figure, whether planned or contingent. Construction and permanent jobs distinguished10 of 2540%Construction jobs and permanent or operating jobs were stated separately. Opening target6 of 2524%A target date for the facility to open or operate. Milestones for construction, power availability, completion or incentive eligibility were coded separately. Explicit dependency among opening targets1 of 617%The release linked the timetable to a project-specific dependency beyond an ordinary qualifier such as "expected". Government record or public filing added a qualification or milestone15 of 2560%A local action, government or regulator release or financial filing added a material qualification or milestone for the project. Any supporting record added a qualification or milestone22 of 2588%The 15 above plus sponsor updates, same-day companion releases and secondary reporting.
Project Blue in Pima County, Arizona, shows why a stated condition matters. The county said the first building could operate in 2027 and that Tucson was expected to annex the site to provide water (Pima County release). Tucson declined annexation on August 6, 2025, and a county memo later tied the revised development approach to air cooling. The reviewed records did not establish a revised opening date.
What does a dollar figure in an announcement cover?
A dollar figure in a data center announcement can cover a parcel of land, a first phase, a multi-building campus, power infrastructure or a statewide program, and the 18 figures in this sample covered all five. The six multi-phase figures came from Project Blue in Arizona, QTS Cedar Rapids, Compass Meridian, the CyrusOne project in Bosque County, Vantage VA4 and CleanArc VA1.
Three of those announcements show how scope differs. The first QTS Cedar Rapids release set a $750 million minimum beside the hiring minimums for the first two phases (Alliant and city release). QTS's August 2025 release gave a $10 billion plan for seven buildings (QTS August release). The $10 billion estimate for Compass Meridian included future tenants' IT equipment across an eight-center plan (Mississippi governor release). Caroline County put the expected capital investment for CleanArc at about $8.8 billion for three buildings, or about $2.93 billion each, including developer, affiliate and tenant spending (Caroline County statement).
Other figures had narrower or broader boundaries. The $48.8 million for Digital Realty in Vernon, California, was the purchase price for a parcel (Klabin transaction release). Homer City's initial figure of more than $10 billion covered power infrastructure and site readiness (Homer City announcement). Google's $4 billion Arkansas figure covered a statewide program through 2027 that included the West Memphis campus, cloud and AI infrastructure and local programs (Google Arkansas announcement).
Table 2. The 18 dollar figures and what each covered. Source: Virgo PR coding of announcements dated January 9 to December 17, 2025.ProjectLocationAnnounced dollarsScope of the figureWhat the release says it covers Google West MemphisWest Memphis, AR$4BRegional bundleStatewide investment through 2027 includes the West Memphis campus, cloud and AI infrastructure, and local programs Beale Project BluePima County, AZ$3.6B+Multi-phase projectEstimated $1.2B construction and $2.4B equipment at build-out Core Scientific AUBix conversionAuburn, AL$135M initial / >$400M totalInitial and broader estimateInitial Core Scientific plan. Broader total includes prospective partner capex Digital Realty Vernon acquisitionVernon, CA$48.8MLand onlyClosed consideration for parcel. No cost estimate for center Hut 8 River BendWest Feliciana Parish, LAUp to $10BInitial phase onlyPhase I includes data center infrastructure QTS Big CedarCedar Rapids, IA$750M minimumMulti-phase projectMinimum city headline for early campus build. First two phases distinguished in job requirements AWS VicksburgWarren County, MS$3BProject scope unspecifiedNew campus plan. Spending phases unspecified Compass MeridianLauderdale County, MS$10BMulti-phase projectEight centers over eight years. Includes future tenants' IT equipment Beale Project ClydesdaleTulsa County, OK$1BProject scope unspecifiedProject capital amount. Jobs paragraph gives five-year initial phase, without expressly limiting $1B to that phase BorderPlex Santa TeresaSanta Teresa, NM$5B constructionMulti-activity bundleProjected decade construction spending for integrated campus including data center, manufacturing and logistics. Separate annual IT and manufacturing equipment figures AWS Energy WayRichmond County, NC$10BProject scope unspecifiedNew cloud/AI campus and multiple centers described. No phase-specific allocation Meta Bowling GreenWood County, OH>$800MFacility scopeOnce-completed investment stated for 715,000 sq ft facility Homer City Energy CampusIndiana County, PA>$10B initialPower and site onlyInitial power infrastructure and site readiness. Future data center development described separately ECP / KKR CyrusOne BosqueBosque County, TXApproaching $4BMulti-phase projectTotal campus estimate. $50B refers to broader partnership Vantage VA4Stafford County, VA$2BMulti-phase projectSpecified 3-building campus and first opening tranche. Statewide $8B is separate CleanArc VA1Caroline County, VAAbout $8.8B full scopeMulti-phase projectAbout $2.93B per building including CleanArc, affiliates and tenants. Possible extra buildings outside agreement scope Meta Beaver DamBeaver Dam, WI>$1BProject scope unspecifiedCampus program. Nearly $200M in energy infrastructure cited separately, without specifying inclusion Related Digital CheyenneCheyenne, WY$1.2BInitial phase onlyFirst building. 115-acre build-out described separately
Later records show that one project can carry several unrelated dollar figures. At River Bend, Louisiana, the state put Phase I at up to $10 billion (Louisiana announcement), Hut 8 reported a lease with a $7.0 billion base-term contract value (Hut 8 lease release), and its Form 10-Q reported $3.25 billion of senior secured notes issued on April 30, 2026 (Hut 8 Form 10-Q). Those three numbers answer different questions: an investment estimate, a contract value and issued debt.
The same pattern appears at Saline Township, Michigan, where Related Digital and Blackstone announced in April 2026 that financing had been secured for the $16 billion project (Blackstone financing announcement). Announced financing does not show how much has been spent, and the reviewed records did not establish an amount spent. In Doña Ana County, New Mexico, the county's July 31, 2026 annual report on the follow-on Project Jupiter industrial revenue bonds documents lease and job requirements and does not restate the original $5 billion as spent (Doña Ana County annual report).
What does a megawatt number need to say?
A megawatt number in a data center announcement needs a label, because the 13 figures in this sample measured utility load, critical IT load, generation, or an unstated basis. Without the label, two announcements with the same number can describe different things.
Five of the 13 releases gave both an initial figure and a larger planned figure. Hut 8 gave 330 MW of initial utility capacity, 245 MW of initial critical IT load and a potential 1,000 MW of utility capacity at River Bend (Louisiana announcement). Related Digital described 88 MW of critical IT capacity in the first Cheyenne building and up to 302 MW across the campus (Related Digital Cheyenne release). LG&E said the first 130 MW of a 400 MW Louisville campus would be available in October 2026, and that date describes power service, not opening (LG&E release).
Planned numbers can be clear while service status stays open. NorthWestern Energy signed a letter of intent with Quantica that gave 500 MW and 1 GW as projected load stages, and the utility reported an ongoing transmission study (NorthWestern Energy release). A later Quantica release described 500 MW of planned renewable generation and battery storage, expandable to 1 GW, which is separate from the utility load projections (Quantica platform release). Yellowstone County's October 2026 road agreement covers wear from access work and well drilling, not data center construction (Yellowstone County agreement).
Homer City shows the generation case. The release described up to 4.5 GW of planned generation from gas turbines, and the Pennsylvania Department of Environmental Protection's air-permit record addresses only the gas-fired generating units, not a data center permit or tenant (Pennsylvania DEP record). Aligned's 72 MW PHX-13 facility in Glendale, Arizona, was announced without a stated basis, and the city's release cited a new 230 kV line, which measures voltage, not capacity (Glendale city release). An independent registry later classified the 72 MW as critical IT (registry record for PHX-13). Core Scientific's 16 MW Auburn figure was identified as gross site capacity in a February 26, 2025 investor presentation filed with the SEC (Core Scientific 8-K exhibit).
Table 3. The 13 power figures, the basis each stated and whether a larger figure was given separately. Source: Virgo PR coding of the original releases.ProjectCapacity reportedBasis stated in the releaseSeparate initial and larger figures Core Scientific AUBix conversion16 MW at launchUnspecifiedNo Aligned PHX-1372 MW first facilityUnspecifiedNo Hut 8 River Bend330 MW utility / 245 MW IT initial / up to 1,000 MW utilityUtility and critical ITYes PowerHouse / Poe Louisville400 MW campus / first 130 MWUtility serviceYes ValorC3 BOI-210 MW new facility / 12 MW Boise marketUnspecifiedNo STACK CHI0236 MWCritical capacityNo Quantica Big Sky500 MW phase 1 / 1 GW growthProjected utility service loadYes Stargate The BarnMore than 1 GWUnspecifiedNo Compass MeridianAbout 500 MWUtility supplyNo Homer City Energy CampusUp to 4.5 GWGenerationNo ECP / KKR CyrusOne Bosque190 MW campus / 144 MW initial ITCampus basis unspecified / initial ITYes Vantage VA4192 MW campusUnspecifiedNo Related Digital Cheyenne88 MW initial / up to 302 MW campusCritical ITYes
For a related look at how companies framed power in public, see Virgo PR's analysis of data center power PR and its comparison of nuclear power deal announcements.
How do construction jobs differ from permanent jobs?
Ten of the 25 announcements stated construction jobs and permanent or operating jobs as separate counts, and the boundaries of those counts differed by project. The permanent figure ranged from 40 jobs in the first Cheyenne phase to about 1,000 direct and indirect positions at Homer City.
At Project Blue, Pima County separated about 180 permanent full-time positions expected at build-out, including contractors, from a minimum of 75 onsite full-time employees under the land agreement (Pima County release). At Saline Township, the release separated more than 450 ongoing onsite roles and 1,500 county-wide supporting roles from more than 2,500 union construction jobs. At Cheyenne, Related Digital attributed more than 700 construction jobs and 40 permanent jobs to Phase I (Cheyenne release).
The Google West Memphis release gave no job counts, while the same-day Arkansas state release distinguished construction jobs from operations jobs (Arkansas state release). In Doña Ana County, the Project Jupiter industrial revenue bond agreements require 775 long-term jobs, and the county's annual report records no such hires as of June 30, 2026, beside a separate forecast of 1,500.
Table 4. The 10 announcements that stated construction and permanent jobs separately. Source: Virgo PR coding of the selected announcement for each project. Companion releases cited in the text were not scored.ProjectConstruction jobs statedPermanent or operating jobs stated Beale Project Blue3,000+ direct and >2,000 indirect during construction180 forecast at build-out including contractors. At least 75 onsite employees in county agreement Hut 8 River BendAbout 1,000 at Phase I peakAt least 75 direct Phase I when operational. LED separately estimates 193 indirect QTS Big CedarHundreds during construction30 full-time minimum, 15 in each of first two phases Stargate The BarnMore than 2,500 union construction jobsMore than 450 onsite and 1,500 county-wide supporting jobs in body Beale Project ClydesdaleThousands during five-year initial build-outUp to 100 permanent roles Meta Bowling Green>1,000 onsite at construction peakAbout 100 permanent jobs Homer City Energy Campus>10,000 direct onsite construction-related jobs for integrated projectAbout 1,000 direct and indirect permanent positions across technology, operations and energy Vantage VA41,100 expectedAt least 50 permanent operating jobs Meta Beaver Dam>1,000 skilled-trade workers onsite at peak>100 operating jobs after opening Related Digital Cheyenne>700 Phase I40 permanent Phase I
Which announcements gave an opening target?
Six of the 25 announcements gave a target for the facility to open or begin operating, and only one of those six tied the target to a project-specific dependency in the release. Table 5 lists the six, with the conditions each release stated.
Table 5. The six announcements that gave an opening or operating target. Source: Virgo PR coding of the original releases.ProjectLocationCalendar and milestone statedDependency stated in the release Beale Project BluePima County, AZFirst building could operate in 2027. Completion expected 2029Tucson consideration and expected annexation for water Hut 8 River BendWest Feliciana Parish, LAOperations expected Q2 2027No express opening condition in LED release ValorC3 BOI-2Boise, IDOperations expected in 2027No express condition ECP / KKR CyrusOne BosqueBosque County, TXOperations expected Q4 2026No express opening condition Vantage VA4Stafford County, VAFirst building late 2027No express condition Meta Beaver DamBeaver Dam, WIExpected online in 2027No express condition
Project Blue, described above, is the one that carried a dependency. The announced date and the later change in its conditions are two separate observations.
The county's August 2025 correspondence identified a proposed Tucson Electric Power service agreement for up to 286 MW (Tucson Electric Power filing). The Arizona Corporation Commission approved the agreement in December 2025, said in January 2026 that its decision stood after rehearing applications (commission statement), and the Arizona Attorney General's office appealed in February 2026. The reviewed records did not establish a revised opening date.
The other five opening targets read as plain forecasts. ECP and KKR gave Q4 2026 as an operations target for Bosque County, Texas (ECP and KKR release). Hut 8's River Bend release gave Q2 2027, ValorC3 gave 2027 for its Boise facility, Vantage gave late 2027 for the first VA4 building, and Meta's Beaver Dam announcement said the site would be online in 2027.
Several of the 19 announcements without an opening target still gave dates for other milestones. Table 6 sorts those dates by what they measure, because a power date, a construction start and an incentive deadline each answer a different question.
Table 6. Dates in the sample that were not opening targets. Source: Virgo PR coding of the original releases and later developer releases.ProjectDate or period statedWhat the date measures PowerHouse and Poe, Louisville, KYFirst 130 MW available in October 2026Power availability for the first part of a 400 MW campus. The release gave no opening date. CleanArc VA1, Caroline County, VASeptember 30, 2027Deadline for the first data hall to be operating to earn a 40% rebate rate for 10 years instead of 25% for 15 years. CleanArc VA1, Caroline County, VAQ1 2027, 2030 and 2033 to 2035Target dates for three 300 MW tranches of grid capacity, from the developer release of November 20, 2025. Quantica Big Sky, Broadview area, MTFirst power as early as 2026, full Phase 1 in 2030Electric service stages. The release said permitting progress governs the electrical timetable and gave no opening date. Related Digital, Cheyenne, WYFirst building completion in late 2026Building completion for an 88 MW first phase. The operations date was not stated. Homer City Energy Campus, Indiana County, PAPower production by 2027Generation milestone that depends on gas turbines, with first deliveries expected in 2026. No data center opening date was given. Amazon, Warren County, MSConstruction expected to begin in 2026Construction start only. Stargate, Saline Township, MIEarly 2026 construction startConstruction start pending Michigan Public Service Commission approval. BorderPlex, Santa Teresa, NMGroundbreaking forecast for 2025Groundbreaking only, inside a decade of projected construction spending. Compass Meridian, Lauderdale County, MSEight-year construction sequenceBuild period for an eight-center plan. No opening date was given.
What did supporting records add to the announcements?
Government records or public filings added a material qualification or milestone for 15 of the 25 projects. The count rose to 22 of 25 when sponsor updates, same-day companion releases and secondary reporting were included. Table 7 compares five announcements with the records that followed them.
Table 7. Five announcements compared with later records. Source: Virgo PR review of the original releases, county, utility, regulator and company records observed November 21, 2026.ProjectAt announcementLater recordsWhat the record establishes Project Blue, Pima County, AZPima County approved a purchase-sale agreement for 290 acres on June 17, 2025 ($20.8 million per the county's announcement). Its $3.6 billion estimate combined $1.2 billion of construction and $2.4 billion of equipment. The first building could operate in 2027 and the site could be complete in 2029. Tucson was expected to consider annexation to provide water. About 180 permanent jobs included contractors, and the county separately described at least 75 onsite full-time employees.Tucson voted against annexation on August 6, 2025. A county memo says developer Beale selected air cooling in September. A proposed Tucson Electric Power agreement was for up to 286 MW. The Arizona Corporation Commission approved it in December 2025, and the Arizona Attorney General's office appealed in February 2026.The route to water service changed. Utility contract approval and the appeal are documented. Closing of the land purchase, operating megawatts and a revised opening date were not established. Hut 8 River Bend, West Feliciana Parish, LAOn December 17, 2025, Louisiana Economic Development put Phase I investment at up to $10 billion, with about 1,000 peak construction workers, at least 75 direct Phase I jobs after opening and a Q2 2027 operations target. The 330 MW of initial utility capacity supported 245 MW of critical IT load. Fluidstack was the tenant, with a Google payment backstop.Hut 8's same-day release described a 15-year lease with a $7.0 billion base-term contract value. Its August 2026 Form 10-Q reported $3.25 billion of senior secured notes issued on April 30, 2026, to finance part of the 245 MW development and substation and to fund reserves.The $10 billion is a phase investment estimate, the $7.0 billion is a lease value and the $3.25 billion is issued debt principal. Operating capacity and realized Phase I spending were not established. QTS Big Cedar, Cedar Rapids, IAOn February 13, 2025, the city and Alliant Energy said QTS would invest at least $750 million. They described a January 28 development agreement, a 612-acre site and at least 30 full-time jobs, 15 in each of the first two phases. QTS would add up to $18 million to a local fund after the first construction phase, over 20 years.QTS's August 2025 release gave a $10 billion plan for seven buildings and more than 2,000 construction and permanent jobs combined. A December 2025 council packet describes an amended and restated development agreement covering several urban renewal areas.The February minimum and the August plan describe different scopes. Realized investment, energization by building and the full operating schedule were not established. Stargate, Saline Township, MIOn October 30, 2025, OpenAI, Oracle and Related Digital announced a campus of more than 1 GW across three buildings, a multibillion-dollar investment and an early 2026 construction start pending Michigan Public Service Commission approval. The body separated more than 2,500 construction jobs from more than 450 ongoing onsite jobs and 1,500 county-wide supporting jobs.The commission's December 18, 2025 issue brief describes approved DTE supply and storage contracts, with a minimum 19-year supply term, minimum billed demand of 80% of contracted monthly use and about 1.4 GW of storage. Related Digital and Blackstone announced financing for the $16 billion project in April 2026, and project partners reported construction underway in June 2026.Utility contract approval, announced financing and the reported start of construction are three separate milestones. The amount spent and the commercial start date were not established. CleanArc VA1, Caroline County, VAThe county said its board approved a performance agreement on August 12, 2025. It described about $8.8 billion of expected investment across three buildings, including tenant spending, and at least 50 full-time jobs at wages of at least 150% of the county average. A 25% rebate on increased tax revenue would run 15 years, rising to 40% for 10 years for the first building if its first data hall was operating by September 30, 2027.CleanArc reported groundbreaking on November 20, 2025, and described 900 MW of grid capacity in three 300 MW tranches targeted for Q1 2027, 2030 and 2033 to 2035. It named three investors: Snowhawk, Nuveen and Townsend Group.Board action defines the three-building incentive scope and the deadline for the higher first-building rebate. Q1 2027 is the first reported grid-power milestone. Rebate receipt and commissioning by phase were not established.
Utility and permit records often explain how a campus is powered before the grid is ready. North Carolina's Department of Environmental Quality issued separate final air permits on August 28, 2026, for 588 emergency backup engines at the Amazon campus in Richmond County and 57 temporary Duke Energy bridge-power engines, and the permit requires Duke's engines to retire after grid connection (North Carolina DEQ announcement). The permits establish authority with conditions, not grid readiness.
In Wisconsin, the Public Service Commission conditionally approved a modified version of Alliant Energy's service agreement with Meta on May 7, 2026, and required reporting and tariff work for future large data center loads (Wisconsin commission release). The review identified the written order but could not access its text. In Nebraska, AAIM's first announcement of its second Hastings-area center in July 2025 gave no commissioning date or megawatt figure (AAIM announcement). A July 15, 2026 release then said the 12.5 MW center had been energized, was operating and had been sold to an unnamed private buyer (AAIM divestiture release).
Entergy's quarterly filing says it executed a February 2025 service agreement for the Amazon Warren County, Mississippi campus (Entergy Form 10-Q). On October 19, 2026, Entergy Arkansas said its agreement with Google covers the original West Memphis project and an expansion, adds a substation and two 230 kV lines, and carries a 2028 in-service target for expansion resources that remained subject to regulatory approval (Entergy Arkansas release).
Three announcements had no added qualification in the reviewed records: PowerHouse and Poe in Louisville, STACK CHI02 in Elk Grove Village, Illinois, and CyrusOne in Bosque County. That finding means no qualifying record was located, not that the announcements were confirmed as built.
What should a data center announcement state?
A data center announcement can be checked later when it states the scope of each dollar figure, the basis and stage of each power figure, the category of each job count and the milestone each date refers to. The sample shows where announcements left those facts open and which later records closed them.
Table 8. What each element of an announcement should state, with an example from the sample. Source: Virgo PR analysis of the 25 announcements.ElementWhat to stateExample from the sample Dollar figureWhether it is a minimum, an estimate, a purchase price or issued debt, and which phases, buildings or tenants it includes.CleanArc: about $8.8 billion across three buildings, about $2.93 billion each, including tenant spending. Power figureWhether it is utility load, critical IT load or generation, and whether it is the first phase or the full campus.Hut 8: 330 MW utility capacity supporting 245 MW critical IT load, with a potential 1,000 MW later. Job countConstruction jobs, permanent onsite jobs and indirect or supporting jobs as separate numbers.Saline Township: 2,500 construction, 450 ongoing onsite and 1,500 county-wide supporting jobs. DateWhich milestone it marks: construction start, power availability, completion or operation.Louisville: first 130 MW of power in October 2026, with no opening date given. DependencyAny approval, annexation, permit or equipment delivery the date relies on.Project Blue: a 2027 first-building date that relied on Tucson annexing the site for water.
- Label every dollar figure with its scope before the release goes out, and say whether tenant equipment is included.
- Give each megawatt figure a basis and a stage, and keep requested, contracted and operating capacity apart.
- Report construction jobs and permanent jobs as separate numbers, and say whether contractors are counted.
- Name the milestone behind each date, and state the dependency in the same sentence as the date.
- Plan a follow-up disclosure for the first record that changes a number, such as a utility approval, a financing close or an energization.
Investors and local officials can compare a release with the filings that follow it, which is why the follow-up step matters. For the public-company side of disclosure, see Virgo PR's explainer on investor relations versus financial PR and its guide to choosing an investor relations firm. Virgo PR's AI infrastructure PR agency page covers the chips, data center and power clients it serves.
Of the six announcements that gave an opening target, one named what the date depended on. A release that states the milestone and its dependency can be verified against the record that follows it, and a release that does not leaves that work to the reader.
How did Virgo PR run this review?
Virgo PR reviewed one 2025 announcement for each of 25 distinct U.S. data center developments, then examined company filings, utility disclosures, local approvals and other records. The sample includes new sites and one conversion, with five cases in each of five geographic groups, and the earliest eligible public announcement located for each project was dated between January 9 and December 17, 2025.
The review recorded a construction forecast, a lease, a utility contract, a financing close and an operational date as distinct milestones. Each announcement was coded 1 if it met a rule and 0 if the criterion was absent. Shares use the denominators in Table 1: 25 for most criteria, 18 for multi-phase dollars, 13 for staged capacity and six for dependencies among opening targets. A document published the same day as the announcement counts as supporting evidence, not as the scored announcement.
The 25 releases differ in purpose and maturity, and the counts describe this purposive sample. The review used records visible through November 21, 2026. A contemporaneous saved copy was unavailable for most live pages, so dates and coverage depend on what was accessible, and later public disclosures could supersede individual records. A phrase such as "not established in reviewed records" means the review located no record, not that the fact is untrue.
Version treatment varied by page. The QTS February 13, 2025 text was recovered from the participating utility, the Homer City sponsor page shows an April 11 update under an April 2 dateline, and the Caroline County statement is a PDF with no separate online timestamp.
Agency disclosure: Virgo PR markets communications services to data center and AI infrastructure businesses. The public record search identified no case-specific Virgo engagement with a sampled project. Private client relationships were outside the review.
Coding for all 25 announcements, with links to each scored release Table 9. Coding of all 25 announcements. Yes means the criterion was met. Source: Virgo PR evidence workbook, records observed November 21, 2026.IDProject and scored releaseAnnouncedDollar figureMulti-phase dollarsMW or GWStaged capacityJob splitOpening targetDependencyAny supporting recordGovernment or filed record A01Google West Memphis release2025-10-02YesNoNoNoNoNoNoYesNo A02Beale Project Blue release2025-06-17YesYesNoNoYesYesYesYesYes A03Core Scientific AUBix conversion release2025-02-19YesNoYesNoNoNoNoYesYes A04Aligned PHX-13 release2025-04-17NoNoYesNoNoNoNoYesNo A05Digital Realty Vernon acquisition release2025-11-04YesNoNoNoNoNoNoYesNo B01Hut 8 River Bend release2025-12-17YesNoYesYesYesYesNoYesYes B02QTS Big Cedar release2025-02-13YesYesNoNoYesNoNoYesYes B03PowerHouse / Poe Louisville release2025-01-16NoNoYesYesNoNoNoNoNo B04ValorC3 BOI-2 release2025-05-05NoNoYesNoNoYesNoYesNo B05STACK CHI02 release2025-03-25NoNoYesNoNoNoNoNoNo C01AWS Vicksburg release2025-11-20YesNoNoNoNoNoNoYesYes C02Quantica Big Sky release2025-07-30NoNoYesYesNoNoNoYesYes C03Stargate The Barn release2025-10-30NoNoYesNoYesNoNoYesYes C04Compass Meridian release2025-01-09YesYesYesNoNoNoNoYesYes C05AAIM second Nebraska center release2025-07-04NoNoNoNoNoNoNoYesNo D01Beale Project Clydesdale release2025-10-31YesNoNoNoYesNoNoYesYes D02BorderPlex Santa Teresa release2025-02-25YesNoNoNoNoNoNoYesYes D03AWS Energy Way release2025-06-04YesNoNoNoNoNoNoYesYes D04Meta Bowling Green release2025-04-09YesNoNoNoYesNoNoYesYes D05Homer City Energy Campus release2025-04-02YesNoYesNoYesNoNoYesYes E01ECP / KKR CyrusOne Bosque release2025-07-30YesYesYesYesNoYesNoNoNo E02Vantage VA4 release2025-11-06YesYesYesNoYesYesNoYesYes E03CleanArc VA1 release2025-08-12YesYesNoNoNoNoNoYesNo E04Meta Beaver Dam release2025-11-12YesNoNoNoYesYesNoYesYes E05Related Digital Cheyenne release2025-10-07YesNoYesYesYesNoNoYesNo
Frequently asked questions
What did the data center announcements disclose?
Of the 25 project announcements, 18 disclosed a dollar figure, 13 gave a project-specific power figure and six gave a target for opening or starting operations. Only one of those six named a condition that could affect the timetable.
How many data center announcements gave an opening date?
Six of the 25 announcements in the sample gave a target for the facility to open or operate. Several others gave dates for groundbreaking, power availability or building completion, which answer different questions.
Is a power date the same as an opening date?
A power date is not an opening date. LG&E said the first 130 MW for a Louisville campus would be available in October 2026, and the release gave no opening date.
What do the different megawatt figures mean?
The 13 power figures in the sample measured utility load, critical IT load, generation or an unstated basis. At River Bend, 330 MW of initial utility capacity supported 245 MW of critical IT load, and a potential 1,000 MW of utility capacity described later scale.
Does a dollar figure mean the money has been spent?
The meaning depends on what the figure covers. Digital Realty's $48.8 million was a closed land purchase. River Bend's up-to-$10 billion was a Phase I estimate.
Do job numbers include permanent jobs?
Ten of the 25 announcements separated construction jobs from permanent or operating jobs. The boundaries differed, for example 180 permanent positions including contractors at Project Blue against 40 permanent jobs for the first Cheyenne phase.
Why do supporting records change what an announcement says?
Government records or public filings added a material qualification or milestone for 15 of the 25 projects, and the count rose to 22 of 25 with sponsor updates, same-day companion releases and secondary reporting. Examples include a utility contract approval, a financing close, an air permit and a company report of energization.
Is this a statistical sample of the industry?
No. The 25 announcements are a purposive sample of U.S. projects first announced in 2025, so the counts describe these projects and not data center announcements generally.
Who ran the study, and is there a conflict of interest?
Virgo PR ran the study and discloses that it markets communications services to data center and AI infrastructure businesses. The public record search identified no case-specific Virgo engagement with a sampled project.